A number of major energy facilities commissioned in Ishkoshim, Shughnon, Rushon and Murghob districts of GBAO


President of Tajikistan Emomali Rahmon commissioned several energy facilities in Khorugh that had been built in Ishkoshim, Shughnon, Rushon and Murghob districts.
Emomali Rahmon commissioned the Qozideh 110/35 kV substation in Qozideh village, Ishkoshim district. The facility was built under the Badakhshan Electrification Project and is intended to strengthen the power grid and improve the reliability of electricity supply in the district.
A 3 MW solar power plant in Shughnon district was also put into operation. According to the information provided, the solar plant in Rozh village is among the major renewable electricity generation facilities in the region and uses 4,752 panels. The head of state also remotely commissioned a 112 kW solar plant in Vranjan village, Rushon district, a 25 kW small hydropower plant in the Bartang area of Rushon, a 15 kW hydropower plant in Devloh village of Barushon jamoat, and two experimental wind power plants with a combined capacity of 200 kW in Tokhtamish village, Murghob district.
At the same site, solar panels with a total capacity of 1,138 kW and battery storage of 590 kWh were also installed. In addition, a 110 kV transmission line in Rushon district, 42 km in length, has been commissioned to help improve the stability and reliability of electricity supply in the area.
Source: Khovar National News Agency